Whitehead Road Projects

Current Update:


Rice Hall
The University of Virginia’s Information Technology Engineering Building on Whitehead Road is currently 32 percent complete.

Structural steel has been topped out. Utility connections as well as the elevated slabwork have reached completion. Mechanical, electrical and plumbing rough-in has commenced. Electrical work will continue at the site.

It is anticipated that three more concrete pours will be made in May & June. Currently decks 1, 2 and 3 have been poured. Metal decking and shear studs are in place on floors 4 and 5.

We regret the need for early morning work and apologize for any inconvenience the work may cause.

Rain will postpone the concrete pours; e-mail updates will continue as the work proceeds.

A map showing the location of the work.

More information

College of Arts and Sciences Research Building
The Physical and Life Sciences Research Building will feature modern looking architecture and finishes. Construction is approximately 41 percent complete. The installation of MTHW building service is complete. The following work is on-going:

  • Interior stud walls on levels B-4.
  • Installation of interior electrical, mechanical and plumbing systems.
  • Exterior curtain wall installation on levels 1-4.
  • Installation of the service elevator.
  • Installation of building vapor barrier and brick veneer.
  • Installation of the roofing system.
  • Demolition work in the Chemistry Building to prepare for the new connector.

Consisting of five stories and intended to provide modern research laboratory facilities, this building is expected to be complete Summer 2011.

More information

Project Overview:


Two U.Va. facilities, a College of Arts and Sciences Research Building and an Information Technology Engineering Building, are being constructed along the north side of Whitehead Road. The buildings are key components in U.Va.’s emphasis on science and technology. 