Processing Local Chair Funds: (LC)

 

1. Deposit to Revenue Project (GL)

What

Who

When

How Do I

Receive cash & initiate deposits to various revenue projects

Various central offices

Within 24 hours of receipt

 

Create manual journal entries

Various central offices

Day of bank deposit

 

Verify deposits have been posted to their respective revenue projects

Various central offices

Available day after journal entry has been processed.

 

 

 

2. Install (allocate funds to) Awards (GA)

What

Who

When

How Do I

Install annual chaired professor research allocations to local chair fund awards in each school

University Budget Office

budget@virginia.edu

At the beginning of the fiscal year as part of the annual BOV approved budget load.

 

Analyze whether chaired professor research projects have carryover balances

Award Manager

At the beginning of each fiscal year

FM Award BBA by Award Manager

Submit ICOM to budget office to request any needed chaired professor research project carryover balances.

Award Manager

At the beginning of each fiscal year

ICOM Request Form

Install carryover balances to the local chair fund awards in each school

University Budget Office

budget@virginia.edu

Upon receiving and approving ICOM request from the Award Manager

 

3. Fund Projects (GA)

What

Who

When

How Do I

Fund $2,000 annual installment to each chair project from LC award

University Budget Office

budget@virginia.edu

At the beginning of the fiscal year as part of the annual BOV approved budget load.

 

Award Manager

After the beginning of the fiscal year, upon notification from the Budget Office that an ICOM has been processed.

Modify Budgets and Funding

  1. Increase or first time (Steps 1-10)
  2. Decrease (Steps 11-42)

 

 

4. Create Budgets (GA)

What

Who

When

How Do I

Budget award-project combination

 

University Budget Office

budget@virginia.edu

At the beginning of the fiscal year as part of the annual BOV approved budget load.

 

Award Manager

         or

Project Manager

(If the Award Manager so delegates.)

After the beginning of the fiscal year, when funding is complete.

 

A.    For projects linked to an award for the first time. Creating Award Budgets

B.    For all existing Award/Projects links: Modify Budgets and Funding (Steps 11-31)

 

5. Manage Accounts (GL & GA)

What

Who

When

How Do I

Monitor and reconcile expenditures

Project Manager

All projects should be reviewed by the tenth (10) working day of each month for the previous month’s activity.


See Review Policy.
See GA Review Procedure.
For more information see:
Reconciliation Class.

FM Expenditure Detail by Project

 

Monitor budget to actual and projected expenditures at the award-project level

Project  Manager

All projects should be reviewed by the tenth (10) working day of each month for the previous month’s activity.


See Review Policy.
See GA Review Procedure.
For more information see:
Reconciliation Class.

FM Project BBA by Expenditure Type

 

Monitor budget to actual and projected expenditures at the award level

Award  Manager

All awards should be reviewed by the tenth (10) working day of each month for the previous month’s activity.


See Review Policy.
See GA Review Procedure.
For more information see:
Reconciliation Class.

FM Award BBA by Award Manager

OR

FM Award BBA by Expenditure Type

 

 

Verify and Troubleshoot as Needed (GL & GA)

What

Who

When

How Do I

To verify installment changes made via ICOM request or as part of the initial fiscal year approved BOV budget load.

Award Manager

As needed

FM Installment Modification by Organization

1.    To confirm award installments are fully funded and budgeted.

2.    To determine budget, expenses, and encumbrances for each award summarized by project.

Award Manager

As needed

UVA PA Installment vs Funding vs Budget vs Expenditure Report

Periodic review to make sure no transactions are posting to your projects through GL

Project Manager

Periodically

GL Only Project Activity Detail