Scope
This procedure covers retroactive cost transfers relating to grant
expenditure adjustments over 90 days old.
This procedure does not cover the treatment of conventional cost transfers
or labor distribution cost transfers. In these cases see Procedure 8-20
and 8-22.
Policy [Top]
VIII.C.1 -- Compliance with Sponsor Requirements
Responsibility [Top]
Departmental personnel are responsible for preparing and submitting
the cost transfer request with the knowledge and approval of the Principal
Investigator.
The Office of Sponsored
Programs is responsible for reviewing and approving cost transfer
requests, and notifying the department if need be.
Distribution [Top]
Department/School Administrator
Central Grants Accountant
Assistant Director for Research Accounting
Ownership [Top]
The Assistant Vice President for Research Administration is responsible
for ensuring that this procedure is necessary, reflects actual practice,
and supports University policy.
Procedure Steps [Top]
This activity is performed whenever departments prepare cost transfers
over 90 days old on grant PTAs.
This procedure continues from 8-20.
- Departments submit an email retroactive request to osp-retro-request@virginia.edu
listserve account.
- When requesting a retroactive cost transfer, please be sure to answer
the following questions:
- Why does this charge belong on the grant to which it is being
moved? In other words, how is it allocable?
- Why was the charge put on the wrong award?
- How are you going to prevent this from happening in the future?
- Why is the cost transfer request over 90 days old, and why did
it take so long to discover the error?
- The requests are required to include the following information:
- The PTAs being charged and credited in the move.
- The date(s) of the expenditure(s) being moved.
- The corresponding transaction number(s).
- The amount and the expenditure type for the expenditures being
moved. This can be summarized by expenditure type.
- The reason why the expenditures should be moved. "To correct
error" or "to transfer to correct project" is not sufficient.
- The reason why the request is over 90 days old.
NOTE: If any of these items are missing the request will be
rejected.
NOTE: No transactions can be processed in Oracle after
the close date of the award.
- Cost transfers involving grant and contract PTAs are reviewed by
OSP, and will be reversed if they do not follow the guidelines above.
- If the cost transfer is reversed, OSP will notify the originating
department.
The following
link
provides guidance in the documentation and processing of Labor Distribution (LD) Adjustments impacting sponsored
projects (G and Z awards). Once this new process has stabilized, this guidance will be absorbed into the University’s
formal procedures. Questions should be directed to the Director of Compliance and Outreach in the Office of Sponsored
Programs, Sharon Brooks.
End of Activity
|