Upgrade Timeline
 
 
Completion of the 1st upgrade September 2, 2003
11.0.3 development freeze September 15, 2003
11.0.3 development freeze September 19, 2003
Completion of high-level analysis impact September 26, 2003
Completion of the 2nd upgrade October 10, 2003
Completion of CRP-I November 19, 2003
Completion of CRP-II February 18, 2004
11i User Fair March 3, 2003
Begin User Training March 22, 2004
Completion of User Acceptance Testing April 5, 2004
GO-LIVE May 3, 2004
   
 