After you have completed the 'Parameters' screen:

1. Click the [Schedule] button.

2. Select 'Once' in the 'Run the Job...' block. This option will allow you to schedule the report to be run at the desired time on the following day.

3. Click [OK.] The report is now scheduled.

Retrieving the Report

4. On the following day login to Oracle using the UVA Request Logs responsibility.

5. Identify the report you submitted:

6. Select the completed report from the 'Reports' screen and click the [View Output] button.

7. When the report is displayed continue with steps 12-16 of Running UVA Concurrent Requests Report to save the reports and email them to support staff.