Four trial
upgrades down, one live
upgrade to go. All the
steps are documented,
all the timing fine-tuned.
The data has been validated.
If there are mismatches,
the causes are being explored,
and solutions are being
pursued. Those solutions
must be in place for User
Acceptance Testing (UAT),
which takes place from
March 16 through April
5.
“Our last trial
upgrade was accomplished
in the prescribed time
frame of 126 hours, around
the clock,” reports
Virginia Evans, Assistant
Vice President for ISDS. “Central
office staff have invested
many hours validating
that the data in the new
11i version matches the
data in Production and
that the system is working
as expected. Oracle is
working very closely with
us to resolve any outstanding
issues.”
UAT will involve approximately
124 central and departmental
staff running approximately
1,800 test scenarios in
the upgraded environment. “We
have anticipated every
type of transaction and
every variation on each
of those transactions
that we can think of,” explains
Barbara Henry, ISDS Director,
HR/Payroll Applications.
“The users involved
in the testing must feel
comfortable that the software
and the reports are working
properly and allowing
them to do the work of
the University,” adds
Shy Hicks, Director, Financial
Applications. “Their
sign-off on the many scenarios
will confirm for us that
we are ready to proceed
with the upgrade.”
“This is the critical
time,” notes Evans. “UAT
is when everything has
to come together to minimize
the possibility of surprises
in the final, ‘real’ upgrade.”
|