SSP Milestones

Track the history and progress of the SSP through its milestones.
 
 
Milestone
Date
Project start date 1/2005
Complete Process Validation Workshops. 175 stakeholders participated in 17 half-day workshops. 8/16/05
Complete vendor research discussions with other Universities and site visits to Ol'Miss (Ol’ Miss (SAP); GaTech (Banner); JMU (PeopleSoft); Stanford (PeopleSoft Student and HR, Oracle Financials); Minnesota (PeopleSoft suite).
11/4/05
Requirements defined. University stakeholders voted in DecisionDirector, web-hosted software. 11/23/05
Governance structure established. 3/1/06
PeopleSoft contract signed. PeopleSoft selected as the software vendor for the new student system. 3/9/06
RFP for consulting services issued. 6/13/06
PeopleSoft training for staff and key stakeholders begins. 7/17/06
Final Critical Strategic Issue of original group resolved. 7/24/06
Local Project Groups created. 10/19/06
Sneak Preview of PeopleSoft Campus Solutions 10/24/06
Module Preview Sessions complete 3/29/07
Campus Community IDP sessions complete 5/28/07
Board of Visitors approval of SSP budget 6/7/07
Functional IDPs begin 7/9/07
Functional IDPs complete 11/28/07
Recruitment and Campus Community roll-out 3/3/08
Applicant roll-out 8/4/08
Course Catalog roll-out 8/4/08
Professional school applicant interfaces roll-out 9/22/08
Graduate school applicant interfaces roll-out 9/29/08
Schedule of Classess roll-out 10/6/08
   
   
 