11i.10 Upgrade Timeline
| Completion of the 1st upgrade | November 11, 2005 |
| Completion of high-level analysis impact | November 30, 2005 |
| Completion of the 2nd upgrade | December 9, 2005 |
| 11.5.9 development freeze | January 2, 2006 |
| Completion of Conference Room Pilot-I | February 23, 2006 |
| Completion of User Acceptance Testing | April 17, 2006 |
| Month-end close | March 31, 5 p.m. |
| Finance, LD users out for 11i.10 upgrade | April 20, noon |
| All users out for 11i.10 upgrade | April 20, 5 p.m. |
| ODS available normal hours | April 20-23 |
| GO-LIVE | April 24, 2006, 7:00 a.m. |