11i.10 Upgrade Timeline

Completion of the 1st upgrade November 11, 2005
Completion of high-level analysis impact November 30, 2005
Completion of the 2nd upgrade December 9, 2005
11.5.9 development freeze January 2, 2006
Completion of Conference Room Pilot-I February 23, 2006
Completion of User Acceptance Testing April 17, 2006
Month-end close March 31, 5 p.m.
Finance, LD users out for 11i.10 upgrade April 20, noon
All users out for 11i.10 upgrade April 20, 5 p.m.
ODS available normal hours April 20-23
GO-LIVE April 24, 2006, 7:00 a.m.